In this page, EGYPTROL is listing information that was originally published by other sources on the internet and identified through a link to the webpage that published the news. EGYPTROL and its staff do not assume any responsibility or liability for the accuracy of the information contained in these sources.

Project Name Description Execution Method Status Feb 2017 References
1 Al-shabab Add-On Conversion 2 X 250 MW Convers. to C. Cycle PGESCo Packages Under Construction http://www.pgesco.com/projects/new-west-damietta-add-on-power-plant-250-mw/

http://www.archirodon.net/project/648/cur

http://www.techint-ingenieria.com/en/news/expansion-al-shabab-power-plant-egypt

2 New West Damietta Add-On Conversion 1 X 250 MW Convers. to C. Cycle PGESCo Packages Under Construction http://www.pgesco.com/projects/al-shabab-add-on-power-plant-500-mw/

http://www.archirodon.net/project/647/cur

http://www.dailynewsegypt.com/2017/01/22/611657/

3 South Helwan 3 X 650 MW Supercritical PP PGESCo Packages Under Construction http://www.pgesco.com/projects/south-helwan-power-plant-3x650-mw/

http://projects.worldbank.org/P117407/eg-helwan-south-power-project?lang=en

4 Cairo West Super Critical 1 X 650 MW Supercritical PP PGESCo Packages In Procurement Phase http://www.dailynewsegypt.com/2015/11/25/saudi-fund-loans-100m-to-expand-west-cairo-power-station/

http://www.arabfund.org/Default.aspx?pageid=487&nid=515

5 Assiut 1 X 650 MW Supercritical PP PGESCo Packages In Procurement Phase https://www.kuwait-fund.org/documents/11433/66693/2017.pdf/94281dd8-8dc9-4787-872d-7a25ec9dacc3

http://www.eehc.gov.eg/eehcportal/Eng/Tenders/ShowTender.aspx?TenderStoryId=36

6 Assiut Conversion 2 X 250 MW Convers. to C. Cycle ORASCOM EPC+Finance Under Construction http://www.orascom.com/investor-relations/press-releases/2016/01/11/Assiut-WD-conversion/

http://www.orascom.com/investor-relations/press-releases/2016/01/11/Assiut-WD-conversion/

http://www.orascom.com/investor-relations/press-releases/2016/01/11/Assiut-WD-conversion/

7 West Damietta Conversion 1 X 250 MW Convers. to C. Cycle ORASCOM EPC+Finance Under Construction http://www.orascom.com/investor-relations/press-releases/2016/01/11/Assiut-WD-conversion/

http://www.orascom.com/investor-relations/press-releases/2016/01/11/Assiut-WD-conversion/

http://www.orascom.com/investor-relations/press-releases/2016/01/11/Assiut-WD-conversion/

8 New Capital 4 X 1200 MW Combined Cycle SIEMENS EPC+Finance Some GTs were Synchronized 2016 https://www.siemens.com/eg/en/home/company/topic-areas/egypt-megaproject.html

9 Burullus 4 X 1200 MW Combined Cycle SIEMENS EPC+Finance Some GTs were Synchronized 2016 https://www.siemens.com/eg/en/home/company/topic-areas/egypt-megaproject.html

10 Beni Suef 4 X 1200 MW Combined Cycle SIEMENS EPC+Finance Some GTs were Synchronized 2016 https://www.siemens.com/eg/en/home/company/topic-areas/egypt-megaproject.html

11 6' October Add-On Conversion 1 x 300 MW ANSALDO EPC+Finance Under Construction http://powernews.cc/%D8%B9%D8%A7%D8%AC%D9%84-%D8%A8%D8%AF%D8%A1-%D8%AA%D9%86%D9%81%D9%8A%D8%B0-%D9%85%D8%B4%D8%B1%D9%88%D8%B9-%D8%A7%D9%84%D8%AF%D9%88%D8%B1%D8%A9-%D8%A7%D9%84%D9%85%D8%B1%D9%83%D8%A8%D8%A9-%D8%A8/ http://www.ansaldoenergia.it/easynews/newsleggi.asp?newsid=110